Forelobige utbetalinger den 30.04.2011 | ||||
Kjopt | Pris I GHC | Avvik fra budsjett | Pris I NOK | Avvik fra budsjett |
| | | | |
Masonary Work | ||||
Binding Wire | 20 | 0 | 74 | 0 |
60 Iron rods | 506 | -19 | 1872 | -71 |
Steroids | 75 | -25 | 278 | -93 |
170 bags cement | 2040 | -360 | 7548 | -1332 |
1700 blocks | 1700 | -300 | 6290 | -1110 |
Gravels | 518 | 68 | 1917 | 252 |
Sand | 625 | -125 | 2313 | -463 |
Transport (cement and water) | 80 | 80 | 296 | 296 |
Payment Mason | 1400 | 0 | 5180 | 0 |
Ironbender | 250 | 250 | 925 | 925 |
20 boards | 120 | 20 | 444 | 74 |
Digging the ground | 100 | 100 | 370 | 370 |
Total | 7434 | -311 | 27506 | -1144 |
| | | | |
Carpenter Work | ||||
Taking down roof | 100 | 100 | 370 | 370 |
2” Nails | 26 | N/A | 96 | N/A |
3” Nails | 78 | N/A | 289 | N/A |
4” Nails | 78 | N/A | 289 | N/A |
5/8 Rod | 60 | N/A | 222 | N/A |
50 Wawa boards | 400 | N/A | 1480 | N/A |
2x6 wood | 2220 | N/A | 8214 | N/A |
Hard wood | 1200 | N/A | 4440 | N/A |
24 Tower bolt | 84 | N/A | 311 | N/A |
Meco Lock | 40 | N/A | 148 | N/A |
Roofing nails | 90 | N/A | 333 | N/A |
40 metal hook | 60 | N/A | 222 | N/A |
Roofing sheet | 1525 | N/A | 5643 | N/A |
Facial board | 713 | N/A | 2638 | N/A |
Payment Carpenter | 1000 | 0 | 3700 | |
Total | 7674 | N/A | 28394 | N/A |
| | | | |
Div. gjenstaar | 600 | N/A | 2220 | N/A |
Total | 8274 | 274 | 30615 | 1014 |
| | | | |
Estimat hele skolen | 15750 | | 58275 | |
Pris hele skolen | 15708 | -42 | 58112 | -163 |
| | | | |
| | | | |
Jeg har startet byggingen av en skole i Ghana, og paa denne bloggen kan man folge utviklingen, lese regnskap og kommentere hvis man lurer paa noe.
Saturday 30 April 2011
Oppdatering 30.04.2011