Resultatregnskap for skole og skolemateriell | ||||
| Pris I GHC | Avvik fra budsjett | Pris I NOK | Avvik fra budsjett |
Amount of money gathered | ||||
Total money | 17800 | N/A | 66400 | N/A |
| | | | |
Mason | ||||
Binding Wire | 20 | 0 | 74 | 0 |
Steroids | 75 | -25 | 278 | -93 |
60 Iron Rods | 506 | -19 | 1872 | -71 |
170 bags cement | 2040 | -360 | 7548 | -1332 |
1700 blocks | 1700 | -300 | 6290 | -1110 |
Gravels | 518 | 68 | 1917 | 252 |
Sand | 625 | -125 | 2313 | -463 |
20 boards | 120 | 20 | 444 | 74 |
Digging the ground | 100 | 100 | 370 | 370 |
Payment Mason | 1400 | 0 | 5180 | 0 |
Payment Ironbender | 250 | 250 | 925 | 925 |
Transport Cement and water | 80 | 80 | 296 | 296 |
Total | 7434 | -311 | 27506 | -1144 |
| | | | |
Carpenter | ||||
2” Nails | 26 | N/A | 96 | N/A |
3” Nails | 78 | N/A | 289 | N/A |
4” Nails | 78 | N/A | 289 | N/A |
5/8 Rod | 60 | N/A | 222 | N/A |
24 Tower bolt | 84 | N/A | 311 | N/A |
Meco Lock | 40 | N/A | 148 | N/A |
Roofing Nails | 90 | N/A | 333 | N/A |
40 Metal hooks | 60 | N/A | 222 | N/A |
64 Steel hinges | 320 | N/A | 1184 | N/A |
Roofing sheet | 1375 | N/A | 5088 | N/A |
Louver blade | 100 | N/A | 370 | N/A |
Louver frame | 50 | N/A | 185 | N/A |
Terpentine | 12 | N/A | 45 | N/A |
Sologram | 25 | N/A | 93 | N/A |
2x6 wood | 2220 | N/A | 8214 | N/A |
Hard wood | 1200 | N/A | 4440 | N/A |
50 Wawa boards | 400 | N/A | 1480 | N/A |
Facial board | 713 | N/A | 2638 | N/A |
Taking down roof | 100 | 100 | 370 | 370 |
Payment carpenter | 1200 | 200 | 4440 | 740 |
Total | 8231 | 231 | 30455 | 855 |
| | | | |
Paint | ||||
2 rollers | 20 | N/A | 74 | N/A |
2 of 6” brush | 10 | N/A | 37 | N/A |
2 of 3” brush | 5 | N/A | 19 | N/A |
2 of 2 ½” brush | 3 | N/A | 11 | N/A |
Scalpel | 5 | N/A | 19 | N/A |
Blue oil paint | 328 | N/A | 1214 | N/A |
White paint | 84 | N/A | 311 | N/A |
Yellow paint | 105 | N/A | 388 | N/A |
Terpentine | 40 | N/A | 148 | N/A |
workmanship | 300 | N/A | 1110 | N/A |
Total | 900 | N/A | 3330 | N/A |
| | | | |
Furniture | ||||
Hard wood | 750 | N/A | 2775 | N/A |
Workmanship | 130 | N/A | 481 | N/A |
Total | 880 | N/A | 3256 | N/A |
| | | | |
Computers for Junior High School | ||||
2 computers | 350 | N/A | 1295 | N/A |
| | | | |
Total price for school | ||||
Total price for building the school | 15665 | -85 | 57960 | -315 |
Total price incl. paint | 16565 | N/A | 61290 | N/A |
Total price incl. furniture & paint | 17445 | N/A | 64547 | N/A |
Total price incl. furniture, paint & 2 computers | 17795 | 0 | 65841 | 0 |
Jeg har startet byggingen av en skole i Ghana, og paa denne bloggen kan man folge utviklingen, lese regnskap og kommentere hvis man lurer paa noe.